1. The purchase of the general accommodation and all general accommodation costs belong to the contracting company.
2. All kinds of non-affiliation documents required for the general settlement of the construction (Building Inspection, No Municipal Debt
The letter of the Social Security Institution, TEDAŞ, TELEKOM, ASAT, the Letter of the Contractors Association, the Letter of Completion of the Work of the Chamber of Architects, etc.)
The contractor belongs to the company.
3. All materials to be used in construction will comply with TSE and C€ standards.
4. Geological survey will be carried out on the plot before the construction permit.
5. The building will be built in accordance with the reinforced concrete static project, ready-mixed concrete will be used.
6. TSE approved iron suitable for static project will be used in construction.
7. 24cm iso brick on the exterior, 8.5cm and/or 13.5cm 1 on the interior. Classroom bricks will be used.
8. The exterior wall plaster will be made with a coarse plaster on the brick and a thin plaster on it.
9. Interior wall plaster, plaster plaster will be made by hitting rough plaster on the brick.
10. The electrical installation will be carried out in accordance with the project. VIKO, MAKEL, METESAN etc. brand any
a key-socket group installation will be performed from one of them. A video intercom system will be installed in each apartment.
An outlet will be installed on the balcony. The satellite dish will be installed. Air conditioning installation will be installed in each room.
11. It will be carried out in accordance with the water installation project. PILSA, AEGEAN, KALDE etc. from any of its brands
our dirty water will be installed under the water plaster. One faucet will be installed on the balcony.
12. Exterior wall paint will be made by applying 2 layers of top coat paint on 1 layer of primer. Paint; FILLI PAINT,
It will be the first quality from POLISAN, MARSHALL, DYO brands or equivalent brands.
13. Interior wall paint, 1 layer BINDER on satin plaster, 2 layers of plastic paint on transparent primer by hitting
will be done.
14. The apartment entrance doors will be steel door or wooden, aluminum according to the interior architectural project, the central lock will be,
the safety lock will be installed.
15. The interior room doors will be MDF (8 mm coated) panel doors, if any, the hall doors will be glazed.
16. The exterior joinery will be 70 series PVC with double glazing. Double openings will be attached to the wings. FIRATPEN, EGEPEN,
ADOPT, ERPEN, etc. it will be one of the pimapen brands or its counterpart.
17. The hall ceilings will be made in accordance with the project.